Tuesday, July 17, 2012

Government Way Road Construction Continues

Due to heavy rains and some materials issues, the Government Way project has experienced some delays.  Crews are now back working to build the roadway up for curb, gutter, and sidewalk along the west side of Government Way.

Two-way traffic is being maintained along Government Way although the speed has been reduced to 25-MPH during construction.  Short delays can be expected, with some activities requiring traffic control and flagging.

Curbing is anticipated to be poured this week.  A paving test strip is planned for the week of July 23rd.  Once the test strip is reviewed and accepted, production paving along the west side of Government Way, Park Road, and Sunup Road will begin.

Access to businesses and residences will continue to be maintained.  During curb and gutter activities, crews may need to build half of the driveway approach at a time to continue keeping access open.

This is an Idaho Transportation Department project, utilizing Federal Highway Administration (FHWA) funds with the City of Coeur d’Alene as the local sponsor. For more information, please contact 769-2228.